Comment: 144 Housing Gate - will there be a west bound turn lane in the project that DPW has planned for later this year?
Answer: 02 May 12 - No, left turns are unsafe at this intersection unless a signal is provided, and a signal is not included in the project. The project will provide deterrents against the numerous illegal u-turns that currently occur in the borning between 0800 and 0900. Instead of making u-turns, Soldiers from the housing area need to use their secondary entrance into the 4IBCT or Gate 3 (rather than Gate 5) to enter the main cantonment area.
Friday, May 4, 2012
06 Apr 2012: CDC Crosswalk
Comment: Need for a crosswalk at our big CDC. (unsure which one specifically--check them all)
Answer: 02 May 12 - All CDCs were checked. CDC on Davis Avenue was the only one where a crosswalk was deemed necessary. Conceptual design is complete with an estimated cost of $7,600.
Update: 08 May 12 - DPW recommending no crosswalk b/c it is essentially to nowhere (nothing on opposite side--sidewalk etc.)
Answer: 02 May 12 - All CDCs were checked. CDC on Davis Avenue was the only one where a crosswalk was deemed necessary. Conceptual design is complete with an estimated cost of $7,600.
Update: 08 May 12 - DPW recommending no crosswalk b/c it is essentially to nowhere (nothing on opposite side--sidewalk etc.)
06 Apr 2012: Gate 3
Comment: Need a light at Gate 3.
Answer: No light is necessary based on traffic flow and density (& reduced speed limit)
Answer: No light is necessary based on traffic flow and density (& reduced speed limit)
06 Apr 2012: Light Timing
Comment: Problems with the timing of the light at 144 and Sundbury.
Answer: 08 Jun 12 - Lights have been adjusted.
Answer: 08 Jun 12 - Lights have been adjusted.
06 Apr 2012: Tank Trail Network
Comment: Can we keep convoys off of 144 and make them use the tank trail network?
Answer: No---safer and efficient to continue on 144.
Answer: No---safer and efficient to continue on 144.
06 Apr 2012: Digital Finger Printing
Comment: Digital finger print machines in security division are down causing us to send people off post at a cost for this service
Answer: 03 May 12 - At no time were customers referred off post. machines were down due to technical issues but both FS and HAAF's have been resolved and are fully operational.
Answer: 03 May 12 - At no time were customers referred off post. machines were down due to technical issues but both FS and HAAF's have been resolved and are fully operational.
28 Apr 2012: GSA Vehicles
Comment: GSA Vehicles - problem with supervisors holding on to credit cards. Without this the operator cannot get towed or repaired.
Answer: 04 May 12 - Each vehicle has a credit card and is signed for by dispatcher. Supervisors should not take this away and TMP should be notified in such instances. Authorization o fthe card will be pre-approved via TMP in the event of a vehicle malfunction.